I followed En. Wahi and En. Yakob teams to Bakri Industrial Area. A factory had problems about the electricity supply. They claimed that TNB doesn'nt supply enough electricity. The Foremen, En. Samzaini took the reading at the meter by using a multimeter. The result are (take phase-to-neutral wire):
- R=213 V
- Y=215V
- B=223V
With the result, it shows that TNB supplies enough electricity to the factory. For single phase, TNB supplies 230 V +- 6%.
Then, we went to new build Police Apartment to set up LPC meters. The setting up of LPC here were challenging because the work space is small.