1. I learnt the flow of a supply project. The flow starts from the receiving of form from the applicant until the budget for the project is approved.
  • if the budget is up to 20K only, the approval can be given by the Branch Manager.
  • if the budget is up to 50K, the approval must be given by the Area Manager.
  • higher budget must be approved by more important person in TNB thus, it will take longer time than a project with lower budget.
2. I followed En. Zulkarnain to site of 10 units shop in Payamas, Tangkak. These shop will be supplied from a feeder pillar which is only 100 meter away.

3. We also went to Sek. Keb Sri Jong to make estimation for its new block.